In California, Aemetis’ CEO said ahead of the quarterly earnings call that progress had continued on the carbon reduction and revenue expansion projects to drive significant revenue increases and positive earnings. For its dairy renewable natural gas project, it completed and tested the first two dairy digesters and began constructing the four-mile pipeline to connect the two dairies to the Keyes ethanol plant. Construction was completed and operation of the carbon dioxide capture system at the Keyes plant to supply the newly-built Messer CO2 plant under a long term contract began. Progress was also made toward commencing construction of the company’s below zero carbon content California waste wood ethanol biorefinery.