Summit Carbon Solutions seeks South Dakota permitting extension

May 11, 2022 |

In South Dakota, AgWeek reports that Summit Carbon Solutions has asked the state’s Public Utilities Commission for an extension for its permitting process to May 16, 2023, as opposed to the February 9, 2023, the date it would normally have to complete everything by based upon its original permitting application date. The PUC on Tuesday added more intervenors to the case and said it would consider more, even though the deadline has passed, if the route changes. The case has a record number of intervenors.