Fiberight may not produce energy until March 2018
In Maine, although Fiberight’s new MSW facility should be ready to accept waste by April 1 according to a new construction timeline, it won’t actually be able to begin processing the waste from more than 100 communities in the state until June when the technology is commissioned. And even then it could take until March […]